OPRAVA SJÍŽĎÁKU (od 15.3.2019)

12. 3. 2019

PŘEDPOKLÁDANÝ HARMONOGRAM PROVEDENÍ PRACÍ

REKONSTRUKCE BETONOVÉ PLOCHY SJÍŽĎÁKU YC BRNO

15.-17. 3. 2019 ----- PROVEDENÍ PŘÍPRAVNÝCH PRACÍ – OHRANIČENÍ PLOCHY SMĚREM DO JEZERA FIXACE KOTEVNÍCH PRVKŮ MOLA, UVOLNĚNÍ PLOCHY OD LODĚ HYKRDA

18.-22. 3. 2019 ----- ŘEZÁNÍ STÁVAJÍCÍ BETONOVÉ PLOCHY, BAGROVÁNÍ A PŘÍPRAVA PLOCHY DEPONIE VYTĚŽENÉHO MATERIÁLU NA SKLÁDKU

22.-30. 3. 2019 ----- BETONÁŽ PLOCHY

 

OD POSLEDNÍHO DNE BETONÁŽE BUDE :

  • 0 AŽ TŘI DNY -- ZÁKAZ VJEZDU A VSTUPU NA PLOCHU.

  • TŘI DNY AŽ JEDEN TÝDEN -- PAK MOŽNÝ VSTUP S LODĚMA NA SLIPÁCÍH.

  • PO JEDNOM TÝDNU -- MOŽNO NATLAČIT VLEK S MOTORÁKEM NA PLOCHU V ŽÁDNÉM PŘÍPADĚ NE AUTEM!

  • PO DVOU TÝDNECH -- MOŽNO VJÍŽDĚT OSOBNÍM AUTEM.

KONTEJNER DOSUD STOJÍCÍ POD SCHODY SE BUDE NADÁLE, VZHLEDEM K ÚNOSNOSTI PLOCHY, UMISŤOVAT U PLOTU NA PŘÍJEZDU.

PRO DOSTATEČNÝ MANIPULAČNÍ PROSTOR PŘI BETONÁŽI JE NUTNO V TERMÍNU 18-30.3 2019 KONTEJNER VYSTĚHOVAT NA PARKOVIŠTĚ ABY NEPŘEKÁŽEL - BUDOU NAJÍŽDĚT MIXY A DALŠÍ TECHNIKA .

 

 

 

Petr AUDY