OPRAVA SJÍŽĎÁKU (od 15.3.2019)
PŘEDPOKLÁDANÝ HARMONOGRAM PROVEDENÍ PRACÍ
REKONSTRUKCE BETONOVÉ PLOCHY SJÍŽĎÁKU YC BRNO
15.-17. 3. 2019 ----- PROVEDENÍ PŘÍPRAVNÝCH PRACÍ – OHRANIČENÍ PLOCHY SMĚREM DO JEZERA FIXACE KOTEVNÍCH PRVKŮ MOLA, UVOLNĚNÍ PLOCHY OD LODĚ HYKRDA
18.-22. 3. 2019 ----- ŘEZÁNÍ STÁVAJÍCÍ BETONOVÉ PLOCHY, BAGROVÁNÍ A PŘÍPRAVA PLOCHY DEPONIE VYTĚŽENÉHO MATERIÁLU NA SKLÁDKU
22.-30. 3. 2019 ----- BETONÁŽ PLOCHY
OD POSLEDNÍHO DNE BETONÁŽE BUDE :
-
0 AŽ TŘI DNY -- ZÁKAZ VJEZDU A VSTUPU NA PLOCHU.
-
TŘI DNY AŽ JEDEN TÝDEN -- PAK MOŽNÝ VSTUP S LODĚMA NA SLIPÁCÍH.
-
PO JEDNOM TÝDNU -- MOŽNO NATLAČIT VLEK S MOTORÁKEM NA PLOCHU V ŽÁDNÉM PŘÍPADĚ NE AUTEM!
-
PO DVOU TÝDNECH -- MOŽNO VJÍŽDĚT OSOBNÍM AUTEM.
KONTEJNER DOSUD STOJÍCÍ POD SCHODY SE BUDE NADÁLE, VZHLEDEM K ÚNOSNOSTI PLOCHY, UMISŤOVAT U PLOTU NA PŘÍJEZDU.
PRO DOSTATEČNÝ MANIPULAČNÍ PROSTOR PŘI BETONÁŽI JE NUTNO V TERMÍNU 18-30.3 2019 KONTEJNER VYSTĚHOVAT NA PARKOVIŠTĚ ABY NEPŘEKÁŽEL - BUDOU NAJÍŽDĚT MIXY A DALŠÍ TECHNIKA .
Petr AUDY